The Schedule Performance Index is equal to: Question 30 options: CV/PV EV/CV EV/PV AC/PV code example
Example: The Schedule Performance Index is equal to: Question 30 options: CV/PV EV/CV EV/PV AC/PV
Schedule Performance Index (SPI) calculation: SPI = EV/PV